It is possible to forward schedule Transports into Production.

The scenario the new functionality aims to address is where an ActiveControl customer has a regular release cycle, but wants to delay specific changes until a specific date/time in the future after the next release. This can now be done via new options available on the Business Task ‘Additional Data’ tab.

Note: Forward Scheduling is complete separate to standard Transport Expresso Schedules configured in the Windows GUI, and does not work in conjunction with any custom field based Selection Criteria rules that you may have setup. This means that if you setup a forward schedule, it will be imported at the specified future date/time, irrespective of any restrictions you have configured as part of standard Transport Expresso Schedules.

Configuration Steps

A customers ‘Production’ Target Role must be assigned to a new ‘Production’ Function within Windows GUI Configuration.
Go to Tools – Configuration – Target Roles and Transport Schedules. If not yet done, create a role
Production’ with the Function ‘Production’ assigned.

It is this function that tells Transport Expresso which is your Production system. No other Target Roles need to be assigned to a Function. (the Development, Test and Merge functions are for future ActiveControl development, and are not currently used for anything)

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment